With more than twelve years of Mission Critical experience, Global Earthwork + Underground is uniquely qualified to understand the fast pace, development changes, and progressive design required to achieve success.
In facilities where continued service is not only expected, but essential, our team understands the importance of delicately managing the project's requirements from the very beginning. Global's leadership team is well-versed in estimating, pre-construction, and progressive design across major Mission Critical campuses across the Midwest.
SLN-2A, SLN 3-A DATA CENTER
Council Bluffs, Iowa
The project consisted of 40,000 feet of pipe varying from 88" to 2" pipe and involved management of work hours, deliveries, sequencing of installation, subcontractor coordination, and additional coordination between pipe crews, trades, and utilities.
PROJECT VELVET DATA CENTER
Kansas City, Missouri
The project consisted of 60,000 feet of water, sewer, and storm piping and involved management of project scheduling, deliveries, equipment utilization, and oversight of subcontractors and all construction activities.
AMAZON DISTRIBUTION CENTER
Kansas City, Kansas | Papillion, Nebraska
This project involved the management and scheduling of all water, sanitary sewer, and storm sewer, while overseeing subcontractors and all construction activities.
ADDITIONAL PROJECT EXPERIENCE INCLUDES:
-
General Contractor: Design-Bid-Build
-
Partner: Design-Build
-
Partner & Subcontractor: Progressive Design-Build
-
Self Perform: earthwork, structural concrete, interior piping, buried piping, paving operations, and mass excavation